Summer Surface Water Lines Start-Up
Start Date
Monday, June 8, 2026 - 7:00 AM
End Date
Until further notice
Active
Last Update: Thursday, June 4, 2026 - 11:10 AM
Water and waterworks
Issued: Thursday, April 30, 2026 - 6:04 PM
Water lines will be turned on, and residents can connect service lines on Monday, June 8th.
Delivery schedules shall remain in place up to and including June 9th, so that residents are not without water during the start-up process
Water mains are currently on, and residents are advised not to turn on valves to their properties. The lines are still being commissioned, and water sampling is currently being conducted.