Browser Compatibility Notification
It appears you are trying to access this site using an outdated browser. As a result, parts of the site may not function properly for you. We recommend updating your browser to its most recent version at your earliest convenience.
Skip to Content
RCMP: 669-1111 Fire & Ambulance: 873-2222

Construction

|
 
Contacts
2019 Capital Projects

Updates for the 2019 Capital Projects will be available in Spring of 2019.

 

2018 Capital Projects

   
2018 Paving - Contract A - Franklin Avenue (Norseman Drive to Old Airport Road)
Contractor:
NWT Construction Ltd.
Status: Complete
 
Work scheduled for 2018 Paving Contract A includes asphalt resurfacing from Norseman Drive to Old Airport Road, curb and gutter replacement, installation of a 3 metre asphalt pathway on each side of the road and improvements to street lighting.
 
Franklin Avenue Phase I & II
Contractor: NWT Construction  Ltd.
Status: Complete
A two year project that was awarded to NWT Construction Ltd. in 2017. Work includes asphalt resurfacing between Norseman Drive and Gitzel Street, replacement of curb and gutter, street lighting upgrades,  installation of a 3 metre asphalt pathway on each side of the street and installation of new bus pullouts. Replacement 350m of Sanitary Sewer Pipe between Forrest Drive and Gitzel Street and replacement of an existing fire hydrant and vault near Pumphouse No. 3.
  
Contractor: ACE Enterprises Ltd.
Status: Calder Crescent Postponed to 2019 
Paving Contract C includes asphalt reaplcement on Calder Crescent, Lamoureux Rd and Finlayson Drive (Between Cinnamon Crt. and Finlayson Crt) . Other acitivity will include installation of curb and gutter and replacement of any existing sidewalks. All streets under this contract are partially funded by the Federal Canadian Water and Waste Water Fund (CWWF).
 
Contractor: NWT Construction  Ltd.
Status: Complete
 
Three projects under Paving Contract D will have the existing gravel roads upgraded to a paved surface. Those projects include Engle Business District Phase I, Grace Lake Blvd., and Northlands Trailer Park Phase I. Streets to be paved under Northlands Trailers Park Phase I include: Anson Drive, Catalina Drive, and Norseman Drive.
 
The forth project under Contract D is paving of Williams Avenue which is intended to reinstate all areas of Williams Avenue, Beck Court and Inukshuk Housing affected by the 2017 Water and Sewer repairs. Work related to Williams Avenue includes installation of a new asphalt surface, new curb and gutter, new concrete sidewalk, and installation of a new asphalt pathway between Williams Avenue and Woolgar Avenue.
 
Contractor: ACE Enterprises Ltd.
Status: Complete

Paving in Block 501 will have the existing gravel roads upgraded to a paved surface. The work includes installation of a new asphalt surface, new curb and gutter and new concrete sidewalk.

 
2018 W&S - Contract A - Dagenais Drive
Contractor: RTL Robinson Ltd.
Status: Complete
 
Contract A - Dagenais Drive will include replacement of approximately 450m of  watermain, sanitary sewer piping and residential services. All fire hydrant vaults within the project area will be also be replaced. The remaining 200m section of Dagenais Drive is scheduled  in 2019.
 
 
Improvements to the School Draw Parking Lot will include installation of approximately 2500 sq. m. of paved parking area for vehicles and boat trailers as well as required hardscaping features.  
 
This project will include relocation of power and communication infrastructure from overhead services to buried services at the intersection of 44th Street and Franklin Avenue. Traffic signals will then be installed and commissioned once all underground work is completed.
Feedback